ARC tunnel project hurt by poor planning
By Karen Rouse
The (Bergen) Record, September 20, 2010

NJ Transit did not have a complete plan for "combating fraud, waste and abuse" or safeguards for keeping its Hudson River tunnel project from spilling over its $8.7 billion budget, a federal audit shows.

Now, the project, which has been put on hold by Governor Christie, could go as much as $5 billion over budget if a plan to mitigate risks is not put in place, according to a
source close to the project.

Auditors also took issue with the Federal Transit Administration's early handling of the
"Access to the Region's Core" project. Even though NJ Transit did not complete a project management plan, master schedule or financial plan, the FTA signed an agreement with the agency allowing it to incur $1.35 billion in costs toward tunnel construction, the audit said.

"Despite lacking fully developed documents, FTA allowed the … construction contract to proceed in June 2009," auditors wrote in a 30-page report issued earlier this year.

That decision by the FTA put the project at risk for cost overruns and delays, auditors wrote repeatedly in the report.

NJ Transit is required to submit project plans to receive $3 billion from the FTA under its "New Starts" program. The money would be the largest amount ever awarded through the program, which funds local, public transit projects like light rail, trolleys and commuter rail.

The report said the lack of documents provided by NJ Transit hindered the FTA's ability to keep NJ Transit accountable.

NJ Transit and FTA officials declined to comment for this story.

The audit, conducted by the U.S. Department of Transportation's inspector general
between January 2009 and March, examines FTA and NJ Transit documents related to cost, scheduling, financing, fraud and other issues. And it possibly sheds some light on
Christie's decision to halt new work for 30 days.

It also reveals early friction between the FTA's Region 2 staff in New York, charged with overseeing the ARC project, and NJ Transit staffers. Transit agency officials complained the FTA was not providing enough guidance in completing the complex series of documents it needed to file to secure the $3 billion.

Funding breakdown

The ARC project calls for the construction of a 9-mile commuter rail line between North
Jersey and Manhattan that runs adjacent to Amtrak's Northeast Rail Corridor. It includes the construction of two new tunnels under the Hudson River, a new underground passenger rail station adjacent to New York's Penn Station, a storage yard and the purchase of passenger rail vehicles and specialized dual-powered locomotives.

The breakdown of funding sources for the project is as follows:

•Port Authority of New York and New Jersey, $3 billion.
•New Jersey Turnpike Authority, $1.25 billion.
•Federal Transit Administration's New Starts Program, $3 billion.
•Federal Highway Administration, $1.3 billion.
•American Recovery and Reinvestment Act, $130 million.

Auditors examined whether NJ Transit had a plan to identify project risks and how to mitigate them, as well as obstacles to funding. They also took a look at the agency's plan for preventing fraud, waste and abuse, according the report.

Among other things, auditors expressed concern that the state's Transportation Trust Fund, which is nearly empty, would not have the money to contribute to ARC.

In an April 6 letter, Christie told Transportation Secretary Ray LaHood that the New Jersey agencies are committed to funding for the ARC project, saying it is "critical for the transit riders of New Jersey and the region."